Case Studies
Fitton Field
Home of the Worcester Tornadoes
Aggressive Timeline, Impressive Results
The Situation |
|
|
It is announced that Worcester, MA will be home to the Worcester Tornadoes, the city’s first professional baseball team in 71 years. |
The Challenge |
|
December 2004 |
Team owners sign a deal with league which requires a completed stadium by May 26, 2005 – just five months. |
Late January 2005 |
Dant Clayton was chosen as the stadium partner based on their reputation for innovation, experience and reliability. |
The Dant Clayton Solution |
|
February 2005 |
The owners provided specifications
on the scope of the project in a preliminary design meeting with Dant
Clayton's engineering team. Though the schedule was extremely aggressive,
Dant Clayton evaluated its capacity, then drafted an action plan and
proposal, which included defined project obstacles and solutions.
|
The Results |
|
May 2005 – Fitton Field Opening Day |
The stadium was finished according to plan—on time and on budget. The final structure looks great, is fully code compliant, and meets all of the needs of the team, fans and community. |
![]() |
![]() |